Going through inspections


Some of the most stessful times during the building of the house was going through the

the inspections that are required in order to get our Occupancy Permit. Since neither

one of us were professional builders we didn't know what to expect. Would the inspectors

be harder on us since we "didn't know what we were doing" or would they be more forgiving

because we "didn't know what we were doing".

This is the piece of paper that let us officially start! This is the building permit

In the area where we are building there are 13 required inspections. The only ones that we

would not be responsible for would be the plumbing, heating, insulation and septic system as

we were doing the rest of the work. That however only eliminated four inspections leaving

us responsible for nine more.

The footer inspection was the first one and gave us a taste for how we thought they all might

go. The inspector pulled up to the basement in his car, looked down at the footers, said

they looked good, gave us an approval slip and left. He didn't measure to make sure we had

tall or wide enough forms, didn't check the amount of rebar or any other items that we thought

the inspector would check. The same thing happened when he came back to inspect the

foundation. Drove up, looked it over, and approved us.

The next inspection was for temporary electric. We had to have an electric meter mounted on

a pole according to the specifications provided. Once that was approved, the local electric

company would hook us up to the power lines at the road. Electricity is very helpful when

building a house! This inspection was done by a different inspector and the first pole that

we set up did not pass the first time. We had to move the 2x4's that braced the pole up two

more feet. The inspector came back the next day and approved us.

They next inspection was the rough plumbing which we didn't have to worry about as the

sub contractor we hired had to take care of that.

The rough plumbing permit

The next one we had to worry about was the electric service inspection. The service inpection

is when you are getting ready to switch over from the temporary electric pole to the breaker

box that is located inside the house. Both the local utility company and the electric inspector

(The same inspector that inspected the temporary electric pole) have to inspect all of the lines

going to the house. A mis-communication between the local utility company and the electric

inspector almost prevented us from being approved the first time, as we had already filled in

the underground trenches that contained the electric cable based on the instructions from the

local utility company.

We needed to dig out the trench and put in a red plastic tape that has the words "Buried Cable"

printed on it before we could fill in the trench. The inspector approved us on the condition that we

correct this problem before he came back for the rough electric inspection. By this time we were

starting to get more comfortable with dealing with the inspectors and what they expected. We also

discovered that they were more than willing to spend time with us and explain what we had to do to

pass the next inspection. We started taking advantage of this and asking lots of questions when

they would come out.

The septic system was installed, inspected and approved after the service inspection.

We sub-contracted out the installation of the septic system and that sub-contractor was

repsonsible for the inspection.

The next inspection was the rough electrical. Same electrical inspector. We had learned from our

previous mistakes, (or the inspector gave up on us) and we passed the first time.

The next inspector was the rough framing inspection. This was a big one for us. We would

see how well we had built the house. By this time, the house was under roof, the siding was

on the house, the plumbing and electric were installed and the basement was poured. It

would not be easy to change much if there was anything wrong with the house. Needless to say

it was a long day before the inspector got there. When the inspector did arrive, he was one

that we had not seen before. It turns out that the inspector that inspected our footers and

foundation and should have conducted the rough framing inspection, had died, so a new

inspector was hired and he was going to be our inspector for the rest of the project.

Overall we did fairly well for doing it ourselves. We only failed 5 things which only 1 was

a major problem. The easy things were that 1) we only put 2 nails instead of 4 nails in all of

our hurricane clips (the clips that attach to the wall and the roof trusses). 2) We did not have

OSB behind our Kitchen soffit so that if a fire would be inside the walls of the kitchen, it

would not spread out into the soffit. 3) Some of the walls were not solid walls anymore because

the heating contractor cut the walls to run their heating ducts, so we had to nail metal strips

across the top edges to re-join the two halves of the walls. 4) We also had termite strips

under the wood beam where it rests on the concrete block walls in the basement, we should have

put metal plates. The problem was solved by jacking up the beam high enough to slide the

termite shield out and slide the metal plate in place of the termite shield.

5) The big problem was the glass block windows in the basement. We had three glass block windows

along the back of the house where the tops of the windows were even with the top of the concrete

block walls, so the termite strip sat right on top of the glass block and the sill plate sat

right on top of that. The floor trusses than sat on top of the sill plate and the inspector

felt that the floor trusses were too heavy and would eventually cause the glass block windows

to collapse, so he wanted us to install 1/2" steel plates that would span across the glass

block windows and rest on the concrete block wall on both sides of the glass block windows.

After he left we spent the next few hours trying to track down someone that would sell us three

1/2" steel plates 12" wide and five feet long. We finally found someone who would make some

up for us and have them ready by 6:00pm that night! Now all we had to do was install them.

We started Saturday morning with the steel plates. First we had to drill out all of the mortar

that was between the glass blocks and the sill plate. We also had to remove a few inches of

termite shield from both sides of the glass block windows where the steel plates were going

to rest on the concrete block. We then had to jack up the sill plate enough that we could

slide in the steel plate. This was accomplished by using a 1/2 ton car jack that we rested in

the window ledge inside the basement. Using sledge hammers we then drove the steel plates

into the slot that has been created by the removal of the glass block mortar and termite shield.

As it turned out, these corrections were not as bad as we thought and we were all done with all

five of our items by the end of the day. We rescheduled the inspector, he came out and approved

our rough frame.

This is the main permit which all of the inspectors sign when they are finished inspecting their area

The next inspection was the insulation inspection which we didn't have to worry about as the

sub contractor we hired was responsible for that.

The next inspection was the Final plumbing inspection which we also didn't have to worry

about as the sub contractor we hired was responsible for that.

The next big inspection for us was the Final electric inspection. During this inspection, all

of the outlets are tested, the Ground fault interupts are tested, the light fixtures are turned

on and off and all of the ground wires are checked. We did not pass this one as we had four

things wrong. 1) We missed putting in an electrical outlet for a section of countertop in the

kitchen (Every section of the counter must have an outlet so you are not dragging cords over

sinks and stoves). 2) The lights we had installed in the closets did not allow enough clearance

if you stack things on a shelf in the closet. 3) The motors for the jet tubs had been grounded to

the ground wire in the eletric outlet, they needed to be grounded to the copper water pipe. 4) The

last item was the thermostat wires going to the furnace were not encased in a protective

sheath. The last item was taken care of by the sub-contractor that we hired to install the

furnace. Once all of the items were fixed, we rescheduled the inspection and passed this

time.

Eleven down, two to go! The next inspection was from the health department. They came out

and took a sample of our water because we had a well instead of city water.

Before the health department came out, the contractor that we hired to drill the well came out

and dumped a whole bunch of chorline down the well to kill any germs that may have crept into

the system while they were drilling the well. We then had to run the water for about 24 hours

throughout the house so that any dirt still in the system would be flushed out. The health

department came out, took a sample and told us to contact them in three days for the results.

We passed.

The big day had finally arrived. We think we are ready for the final inspection. We have went

over everything twice, cleaned the place up and got ready to wait for the inspector. The

inspection goes very smoothly and he could only find two things wrong with the entire house.

The final inspection rejection notice

The first thing involved the steel posts and the wood beam. The part of the steel posts that

the wood beam sits on has nail holes, we did not put any nails in the holes. The second item

was that there was no drip leg on the gas line going into the furnace. A drip leg is a piece

of pipe that catches any moisture that might be in the gas line before it gets to the pilot

light. This keeps the pilot light from going out which then might let gas escape into the

house. The first one we could fix and the inspector told us that if that was the only problem

he would have passed us. The second problem though was something the contractor that installed

the furnace would have to fix, so we called them. Once we explained what the problem was, they

had us take all of the plastic covers to the furnace off, it was then that we discovered that

the drip leg was already there. We attempted to get the inspector back the same day, but we

were unable to do so. We had to reschedule the inspection for Monday (it was Friday). When he

did come back, everything was approved and we went to get our occupancy permit.

This is the Certiciate of Occupancy. It was what we spent 10 months working towards!

We officially did it, we had built our house from start to almost finish (we still had to install

carpet and trim) in 10 months while both of us still maintained full time jobs. In addition, we

had a lot of help from our friends and family.


Go to the next stage-Installing Wood Doors, Window and baseboard trim

Return to the list of stages

Return to the main page